Contracting Authority

SNCF Gare et Connexion

Project manager

Conception et réalisation LMPR

Contractual period

Phase 1: 7 weeks

Phase 2 : 7 weeks

Key words

Cergy prefecture station

Nature of works:

Cleaning, asbestos removal and rehabilitation of the station

Missions:

Cleaning work on existing architectural false ceilings. 

Construction of a 250 ml work train, removal of 9600m² of sprayed plaster, rehabilitation work with strong weak current, 2-hour CF projection, architectural false ceilings

Specificity:

Station in operation

Track in activity by alternation