Contracting Authority

SCI Magnum

Contractual period

3 months

Key words

Magnum building – Levallois-Perret

Nature of works:

Removal of slabs at the bottom of the formwork with a specific presence on the underside of high slabs

Missions:

The AC plates serving as the formwork bottom are partially present on the site and are covered with a non-asbestos plaster smoothing plaster or fibralite plates.

To allow an exhaustive localization of these plates, a sanding of the non-asbestos coating will be carried out under asbestos condition and the fibralith plates will be deposited.

The AC plates thus exposed will then be deposited by chiselling carried out in a humid environment (approximately 480 ml)

Specificity: