Contracting Authority

SCCV Naraya

Project manager

SADEL Ingénierie

Contractual period

5 months

Key words

SCCV Naraya – Suresnes

Nature of works:

Asbestos removal before works in an office building with 8 floors on 3 basement levels in the city center of Suresnes

Missions:

13537m2 of coating on concrete to be treated:

* 632m2 on walls

* 7155m2 on the ceilings of the superstructure

* 5750m2 on parking lot ceilings

Specificity:

Busy environment

City center (highly urbanized environment)